Introduction - bm522-project-management-cw1-assignment-43696
Project management is defined as a concept which includes applying the knowledge, tools and skills required for accomplishing the project successfully. The current project relates to organising the music event d Lancs Life at Townley Park for promoting the local band and music. The current report will outline the business case along with developing the Gantt chart for the activities. Further, the stakeholder analysis and risk matrix will be present and at last quality analysis will be done.
Experience stress-free academics with our reliable Assignment Helper team! We combine expertise, dedication, and timely delivery to ensure your complete satisfaction and academic growth.
TASK 1
Business case
| project title: "Lancs Life” |
| Project aim: the current project aims to effectively deliver the music festival d Lancs Life within Townley Park |
Project objective
- The objective of the current project is to promote live music by hosting a music event at Townley Park in Burnley.
- Another objective of the current project is to promote local bands in Lancashire to promote the concept of live music.
|
Project deliverable
- The major deliverable of the project is to promote live music among the people so that local music is promoted.
- Another deliverable of the current project is that this event is organised as a not-for-profit purpose and all the excess revenue will be donated to charities within Lancashire.
|
Benefits
- Promoting the local music among the people so that the local rituals and working of the community are promoted among youth.
|
Constraint
- The major constraint in the current project is related to the cost that is whether the project will be accomplished at the given cost or not.
|
Further to make the project successful an effective type of methodology for completing the project must be used. For the organising of the current project of a music event, the methodology of Agile is most suitable. It is a type of methodology which aims at breaking the project into smaller phases so that the project objectives can be attained. The major focus of this methodology is on continuous collaboration and on improving the working of the project (Ulusoy et al, 2021). The rationale for selecting the current methodology is that it makes the work much simpler by breaking the work into smaller stages and helps in the successful completion of the project. For example, Cisco has also shifted to agile to make the billing better. This has benefitted the company well and as a result of this, they can manage the working better and attain more profits. Similarly, complying with Agile will benefit the current event of music by providing better planning and will help in accomplishing the planned objectives.
TASK 2
Work breakdown structure
TASK 3
Developing network diagram
| Task Mode |
Task Name |
Duration |
Start |
Finish |
Predecessors |
Text1 |
Text2 |
Text3 |
Text4 |
| 1 |
Budget Approval |
1 day |
Tue 10-12-24 |
Tue 10-12-24 |
1 |
2 |
1 |
2 |
| 2 |
Hire Publicity Team |
14 days |
Wed 11-12-24 |
Mon 30-12-24 |
1 |
2 |
16 |
2 |
16 |
| 3 |
Hire event designer |
14 days |
Wed 11-12-24 |
Mon 30-12-24 |
1 |
2 |
16 |
94 |
108 |
| 4 |
Check event availability |
8 days |
Tue 31-12-24 |
Tue 18-03-25 |
2,1 |
16 |
72 |
16 |
72 |
| 5 |
Hire event location |
7 days |
Wed 19-03-25 |
Thu 27-03-25 |
4,1 |
72 |
79 |
72 |
79 |
| 6 |
Hire Event Crew |
28 days |
Fri 28-03-25 |
Tue 06-05-25 |
5 |
79 |
107 |
79 |
107 |
| 7 |
Event Design |
14 days |
Wed 07-05-25 |
Mon 26-05-25 |
3,6 |
107 |
121 |
108 |
122 |
| 8 |
Train event crew |
14 days |
Wed 07-05-25 |
Mon 26-05-25 |
3,6 |
107 |
121 |
138 |
152 |
| 9 |
Advertise event & set up a website |
5 days |
Wed 07-05-25 |
Tue 13-05-25 |
2,4,6 |
107 |
112 |
107 |
112 |
| 10 |
Get the public to sign up for the event |
44 days |
Wed 14-05-25 |
Mon 14-07-25 |
9 |
112 |
156 |
112 |
156 |
| 11 |
Sign up guest celebrities to be at the event |
14 days |
Wed 19-03-25 |
Mon 07-04-25 |
2,4 |
72 |
86 |
98 |
112 |
| 12 |
Invite tendering from concession stands |
22 days |
Tue 27-05-25 |
Wed 25-06-25 |
7 |
121 |
143 |
122 |
144 |
| 13 |
Photograph Bands and Crew & Collect Biographies |
15 days |
Tue 08-04-25 |
Mon 28-04-25 |
11 |
86 |
101 |
133 |
148 |
| 14 |
Planning of the performer’s appearance times. |
1 day |
Tue 29-04-25 |
Tue 29-04-25 |
11,13 |
101 |
102 |
148 |
149 |
| 15 |
Printing |
5 days |
Wed 30-04-25 |
Tue 06-05-25 |
14 |
102 |
107 |
149 |
154 |
| 16 |
Advertising Plan and list of performers |
14 days |
Tue 08-04-25 |
Fri 25-04-25 |
4,11 |
86 |
100 |
112 |
126 |
| 17 |
Apply for music and appropriate licences. |
28 days |
Mon 28-04-25 |
Wed 04-06-25 |
16,1 |
100 |
128 |
126 |
154 |
| 18 |
Stage construction |
3 days |
Thu 26-06-25 |
Mon 30-06-25 |
12 |
143 |
146 |
144 |
147 |
| 19 |
Finalise the performers' appearance times. |
7 days |
Wed 30-04-25 |
Thu 08-05-25 |
14 |
102 |
109 |
149 |
156 |
| 20 |
Final Event design alterations and sign-off. |
5 days |
Tue 01-07-25 |
Mon 07-07-25 |
7,18 |
146 |
151 |
147 |
152 |
| 21 |
Soundcheck |
2 days |
Tue 08-07-25 |
Wed 09-07-25 |
8,11,18,20 |
151 |
153 |
152 |
154 |
| 22 |
Event |
2 days |
Thu 10-07-25 |
Fri 11-07-25 |
15,17,21 |
153 |
155 |
154 |
156 |
Path 1
1, 2, 9, 10
1 + 14 + 5 + 44= 64 days
Path 2
1, 2, 4, 5, 6, 9, 10
1 + 14 + 8 + 7 + 5 + 44= 79 days
Path 3
1,4,5,6,9,10
1 + 8 + 7 + 28 + 5 + 44 = 93 days
Path 4
1, 5, 6, 9, 10
1 + 7 + 28 + 5 + 44 = 85 days
Path 5
1, 2, 4, 9, 10
1 + 14 + 8 + 5 + 44= 72 days
Thus, with the analysis of the above table, it is clear that the critical path is path 1 as this is the shortest period in which the objectives will be attained (Soleymani et al, 2022). However, the total time duration for the completion of the project is 272 days which is far more than the critical path. Thus, when the company follows the critical path 1 then the objectives of the project will be attained and project will become successful.
TASK 4
Undertaking stakeholder analysis
| Stakeholder |
Type |
Power |
Interest |
Communication strategy /engagement plan |
| Project manager |
Internal |
High |
High |
Twice written reporting in a day is done to the project manager for every work done. |
| Project team |
Internal |
Low |
Low |
Hourly communication is done among the team so that better-coordinated work is done (Dewanty and Putra, 2024). |
| Project sponsor |
Internal |
High |
Low |
Twice a month, an update relating to money invested is shared through email. |
| Management |
Internal |
Moderate |
High |
Every fortnightly report is shared with the management through company email so that they can review the work well. |
| Finance manager |
Internal |
Moderate |
High |
Weekly update on usage of money and budget is shared via email (Wang, Hu and Tang, 2020). |
| Government |
External |
Low |
High |
At the end of every financial year, the annual report is sent via email to assess the tax obligation. |
| Competitor |
External |
Low |
High |
Annual reports are shared with competitors to compare the performance |
| Customer |
External |
Low |
High |
At every year's end, annual reports are published so that consumers can review the work of the company. |
| Supplier |
External |
Moderate |
High |
Every month, the stock and inventory report and requirements are communicated using verbal and written methods. |
| Legal community |
External |
Low |
Moderate |
For this, legal advisors are also circulated with annual reports so that they can assess the regulatory and legal compliance is made accurately or not. |
TASK 5
Developing risk analysis matrix
| Risk |
Likelihood |
Impact |
Mitigating strategy |
| Financial |
Moderate |
High |
To reduce the chances of financial risk, an effective contingency fund is kept aside and every month’s 2 % profit is entered into that fund so that it can be utilised in case of any emergency (Manoharan et al, 2024). |
| Technical |
High |
Moderate |
For this, a sound research and development department is recruited who work on assessing the technical changes within the environment and implementing the necessary changes. |
| Operational |
Low |
Moderate |
For this, the operational manager is recruited who oversee all the operational activities and related aspects. |
| Strategic |
Low |
Low |
To mitigate this, the strategic officer is hired who checks that every strategy is implemented in the intended manner and also the objective is attained appropriately. |
| Market change |
Moderate |
High |
For this good research analyst will be recruited who will evaluate every market change and in case it will be relevant for the company then it will be implemented (Nwadigo et al, 2022). |
| Change in need of employees |
High |
High |
For this, a coordinator will be recruited who will take feedback from employees at every month's end to know their opinions relating to the company and its policies. |
| Employee resistance |
High |
High |
For this involvement of employees in employee engagement activities and motivational activities will be made so that no resistance will be present. |
| Natural risk |
Low |
Low |
For this, effective analysis of the forecast and weather reports will be done to plan for any contingency. |
| Legal risk |
Low |
Low |
For this, regular compliance checks will be made to assess that all the regulatory aspects are met effectively (Dasović, Galić and Klanšek, 2020). |
| Economic |
High |
Low |
For this risk management, every economic change will be recorded and its impact on the company will be analysed so that better decisions can be taken. |
| Security |
Moderate |
Low |
To mitigate this appropriate security management will be done. |
| Reputational |
Low |
Low |
For this, an effective marketing campaign will be organized to enhance the reputation of the company. |
| Political |
Low |
Moderate |
For this, a check on the political changes will be made and all the necessary changes will be implemented into the working. |
| Liquidity |
Moderate |
Low |
To manage this risk, more emphasis on current assets will be made so that in case of emergency they can be converted into cash (Patel and Nema, 2023). |
| Compliance |
Low |
Low |
For this, every month compliance report will be prepared which will ensure that every rule and law is complied well or not. |
TASK 6
Quality expectation, acceptance criteria, quality specification and control measures
| Quality expectation |
Acceptance criteria |
Quality specification |
For making the project successful the quality must be maintained. The quality expectation is stated as the aspect which needs to be followed to ensure that project objectives are set effectively (El-Khatib et al, 2023). The quality expectations which need to be fulfilled for Lancs Life are as follows-- Generate maximum tickets
- Enhanced publicity of local live music
- Attaining better selling of more tickets
- Certifications for event
- Effective designing of the area of the event
|
The criteria for acceptance are defined as the aspects which need to be fulfilled to make the project successful. In the current case of Lancs Life the acceptance criteria for getting successful are as follows-- All the tickets are sold
- An effective user acceptance process is followed (Isah and Kim, 2021).
- Proper arrangement for food and water is also made during the event.
- Compliance with all health and safety aspects is present
- Project sign off
|
It is stated as the necessary aspect of quality so that the objective of the project can be attained well (Ongpeng et al, 2021). In case quality specifications are not met well then it will impact the overall working. The quality specifications are as follows-- There will not be any technical breakdown during the event
- A good environment will be created
- Snacks and water will be available throughout the event
- Work to be accomplished in estimated cost only
- Estimated that activities will go as per the plan.
|
Control measure- this is the most critical step in making the project successful. If case-effective controlling is not done well then it will affect the work and might be possible that the project is not accomplished well (Dasović and Klanšek, 2021). To control the current project of a music festival, compliance with benchmarking is made. Under this method, various benchmarks are set and the actual performance is compared against it. The different control measures are as follows-
- Ensuring risk management is followed well
- Proper regulatory compliance is made and ensured that all health and safety issues are checked
- Proper budgets are set so that work is managed well.
- Effective KPI and other benchmarks are set so that performance can be analysed
- Clear and effective communication is made throughout the organising of the event.
CONCLUSION
Lastly it is concluded that applying the project management knowledge is very crucial for making the project successful. The study highlighted that complying with project management, the business case is developed and also the working is improved. Moreover, the different stakeholder were identified along with the ways of engagement like the direct communication, through mail and other ways.
REFERENCES
Books and Journals
- Dasović, B. and Klanšek, U., 2021. Integration of mixed-integer nonlinear program and project management tool to support sustainable cost-optimal construction scheduling. Sustainability, 13(21), p.12173.
- Dasović, B., Galić, M. and Klanšek, U., 2020. A survey on the integration of optimization and project management tools for sustainable construction scheduling. Sustainability, 12(8), p.3405.
- Dewanty, M.P. and Putra, I.N.D.P., 2024. Cost Budget Analysis for Equal Distribution of Labour for Multi-Storey Buildings Construction. Sustainable Civil Building Management and Engineering Journal, 1(3), pp.15-15.
- El Khatib, M., Mahmood, A., Al Azizi, A., Al Marzooqi, A., Al Abdooli, K., Al Marzooqi, S., Al Jasmi, S., Alzoubi, H.M. and Alshurideh, M., 2023. A Trial to Improve Program Management in Government Bodies Through Focusing on Program Resource Management: Cases from UAE. In The Effect of Information Technology on Business and Marketing Intelligence Systems (pp. 1315-1340). Cham: Springer International Publishing.
- Isah, M.A. and Kim, B.S., 2021. Integrating schedule risk analysis with multi-skilled resource scheduling to improve resource-constrained project scheduling problems. Applied Sciences, 11(2), p.650.
- Manoharan, K., Dissanayake, P., Pathirana, C., Deegahawature, D. and Silva, R., 2024. Investigating and determining the crucial construction site supervisory competencies influencing the effectiveness of building construction project activities. International Journal of Industrial Engineering and Operations Management, 6(1), pp.43-63.
- Nwadigo, O.B.K., Naismith, N., GhaffarianHoseini, A., GhaffarianHoseini, A. and Tookey, J., 2022. Construction project planning and scheduling as a dynamic system: a content analysis of the current status, technologies and forward action. Smart and Sustainable Built Environment, 11(4), pp.972-995.
- Ongpeng, J.M.C., Layese, V.M.I., Atienza, A.M., Bagaforo, J.C., Diaz, K.C., Aviso, K.B. and Tan, R.R., 2021. Sustainable project schedule management using pinch analysis. Chemical Engineering Transactions, 88, pp.97-102.
- Patel, R. and Nema, A., 2023. Project Monitoring and Scheduling of Water Supply Project Using Primavera P6-A Review. International Journal of Scientific Research in Civil Engineering, 7(1), pp.53-59.
- Soleymani, M., Bonyani, M. and Attarzadeh, M., 2022. Autonomous Resource Management in Construction Companies Using Deep Reinforcement Learning Based on IoT. arXiv preprint arXiv:2208.08087.
- Ulusoy, G., Hazır, Ö., Ulusoy, G. and Hazır, Ö., 2021. Introduction to Project Modeling and Planning (pp. 1-21). Springer International Publishing.
- Wang, Z., Hu, Z. and Tang, Y., 2020. Float-based resource levelling optimization of linear projects. IEEE Access, 8, pp.176997-177020.